Two big generators now back the same project
Datagrid's planned AI campus at North Makarewa, just north of Invercargill, now has both of New Zealand's largest renewable generators as shareholders. Meridian Energy filed its deal with the NZX at 7:30pm on 25 November 2026. It's paying US$30 million for 11.27% of Datagrid Holding Group NZ Ltd, and the NZ Herald puts that at about NZ$54m. Meridian chief executive Mike Roan also joins Datagrid's board, where he'll sit alongside Mercury's Stew Hamilton.
Mercury got there first. In July it paid the same US$30m (about NZ$53m at the time) for 12.7%. Mercury's money was earmarked for early "horizontal construction", which means site preparation. Meridian's tie to Datagrid goes back further, though. The project launched in 2020 and Meridian has worked with it since then.
Meridian's filing includes a footnote saying the two generators came in at different stages and on different terms, especially around the equity each might end up holding. So we wouldn't read the headline percentages as final. That also explains why the valuations reported this week differ: the Herald calculates NZ$478m, while Newsroom says US$266m, or NZ$485m.
What the power option covers
Datagrid's equity deal comes bundled with a 140MW power purchase option. If Datagrid exercises it, Meridian supplies power for 15 years, with supply starting at some point between 1 July 2028 and 1 January 2029. Mercury signed a matching 140MW option in July, so Datagrid has 280MW in options across the two companies.
Neither option is final yet. Each one needs clearance from the Electricity Authority under its Materially Large Contracts regime, which the Authority uses to check very large supply deals before they go ahead. Meridian told the Herald its share fits inside its existing generation. It's also building new capacity, including the 130MW Ruakākā solar farm due next year. Mercury has said its 140MW could come from renewable projects it's still building.
Roan described the campus as "a significant source of long-term electricity demand" that supports Meridian's spending on new renewables. DataCenterNews Asia reports Meridian's view that big long-term customers can help pay for new generation by committing to buy part of its output, and that it doesn't want this kind of demand to come at the expense of existing households and businesses. Meridian has had a team spending 18 months looking at smelters, mineral processing and green fertiliser as other large loads.
The scale and the engineering
The figure in Meridian's filing is 300MW. 1News says that would make Makarewa the second-largest electricity user in the country, behind only the Tiwai Point smelter. For comparison, the Herald cites Fitch's count of 60 data centres in New Zealand with 170MW of capacity between them. One campus would outsize the whole current fleet.
The numbers move depending on where you look. Datagrid's website still says 280MW. The Herald also reports a longer-term goal of growing the 78,000 square metre site to 1GW. Rémi Galasso, Datagrid's chief executive, told Newsroom the first stage would cost NZ$5 billion.
Newsroom reports that Datagrid's building the campus for dense GPU clusters running AI training, inference and high-performance computing. The company hasn't named a chip supplier. Reseller News reports two efficiency targets that lean on Southland's cool climate:
- PUE of 1.1. Power usage effectiveness divides the site's total energy use by what the IT gear itself draws. At 1.1, cooling, conversion losses and lighting add roughly 10% on top.
- WUE of 0.02. Water usage effectiveness counts litres of water per kilowatt-hour of IT load. Datagrid says this would set a benchmark for the Asia Pacific region.
These are design goals for a site that hasn't been built, so we'd treat them as claims until there's operating data.
The grid work is further along. Newsroom says Datagrid has paid Transpower upfront for four high-voltage transformers, bushings and other long-lead parts for a 360MVA substation. Transpower aims to have it commissioned by late 2027, connected to the 220kV lines that already carry power from Manapōuri to Tiwai Point. HEB Construction began earthworks in August.
What's still open
The biggest gap is the final investment decision. Meridian's filing is clear that the project depends on one, and neither the Herald nor Newsroom could get a date. Galasso said in July that funding would come "primarily around credit finance". He hasn't said how much capital Datagrid's trying to raise.
There are no tenants either. Emily Reeve, Datagrid's head of corporate, told Newsroom that tenancy talks are confidential. Newsroom reports industry speculation that the buyers would be a handful of large overseas corporations, as opposed to colocation firms renting space to cloud providers.
International connectivity has shrunk. The original Tasman Ring was meant to loop Hobart, Sydney, Auckland and Taranaki. After Chorus pulled out as a partner, Datagrid scaled it back to a "Phase One" plan and is now seeking money for an Invercargill to Melbourne cable. So far only a marine survey has funding.
Local support isn't settled. 1News reports that hundreds of people came to a community meeting in Invercargill in July with concerns about power supply, noise and consultation. The Green Party wants a one-year pause on consents for new AI data centres.
The US chip rule in the background
From 19 November 2026, the US Bureau of Industry and Security's interim final rule, "Addressing Remote Access to Advanced Semiconductors", applies to data centres everywhere. Here's what Morgan Lewis says it does:
- Operators need a US licence to provide more than 12 million aggregate TPP (total processing performance) to companies headquartered in Macau or a Country Group D:5 country such as China, or whose ultimate parent is based there.
- Morgan Lewis estimates the line at about 760 H100 or H200 GPUs, or just over 200 GPUs in GB300 NVL72 racks. It's measured on hardware, and inference capacity can count.
- Sites already serving covered customers have 90 days to actually hold a licence. Having an application in doesn't count.
- Operators are expected to check direct and indirect ownership. If a customer won't share enough detail, that's treated as a red flag.
- The obligations pass down to later owners of the hardware.
- Brazil, Indonesia, Malaysia, Singapore and Thailand now need licences for advanced chip exports. New Zealand and Australia aren't on that list.
Reeve told Newsroom that Datagrid doesn't expect the rule to cause it problems. Newsroom points out that it does rule out Chinese companies as tenants.
What this means for builders here
Plan around today's capacity. Power under Meridian's option can't flow before July 2028, and there's still no build decision. Teams sizing GPU work for 2027 should rely on the existing 170MW onshore fleet and offshore cloud regions.
Don't assume small-scale access. Everything reported points to a few large wholesale tenants. Nobody has said whether an Auckland startup could rent a handful of nodes, directly or through a reseller, so we'd treat that as unknown.
Get your ownership paperwork ready. The US rule already applies to any GPU provider in New Zealand or Australia running clusters above the line. If your company or your clients have a parent based in China or Macau, expect longer onboarding questions, and possibly refusals.
Watch four milestones. These are Electricity Authority decisions on both 140MW options, a final investment decision, a named tenant and funding for the Melbourne cable. Together they'll show whether Southland gets a training-scale campus this decade.
Sources
- Meridian secures 11.27% stake in Datagrid (NZX announcement)
- Commerce Targets Remote Access to Advanced Semiconductors in New Interim Final Rule (Morgan Lewis)
- Gentailers gamble on big AI factory, despite Trump crackdown (Newsroom)
- Meridian buys 11.3% stake in Southland "AI factory" maker Datagrid for $54m (NZ Herald)
- Meridian buys stake in Southland AI data centre, joining Mercury (1News)
- Meridian takes US$30M stake in Datagrid (Reseller News)
- Meridian invests in Datagrid Southland data centre (DataCenterNews Asia)